Consultation information


Introduction

Fawley Waterside Limited is bringing forward proposals for the former Fawley Power Station site, transforming it into a modern hub for jobs, innovation and energy.

Following our consultation earlier this summer, we have reviewed feedback and carried out further surveys and work to help refine our proposals ahead of our planning application submission in autumn this year.

We are hosting this further consultation to continue our engagement with the local community, stakeholders and interested parties, ensuring we develop a project that delivers long-term benefits for the local area.

Have Your Say

We would like to hear your views on our updated proposals for Fawley Waterside. The public consultation is open from Tuesday 29 September until Sunday 18 October 2026.

Complete our survey here

The Team

Fawley Waterside Limited is working with a team of specialists to develop the proposals for Fawley Waterside. Members of the project team are on hand to answer questions and provide further information on the plans. The team comprises:

Development Manager

Masterplanner and Architect

Planning Consultant

Ecology Consultant

Heritage & Archaeology Consultant

Environmental Specialist

Community Engagement

Traffic and Transport

Landscape & Visual Impact Consultant

Arboricultural Consultant

You Said, We Did

Following our previous round of consultation, we have reviewed feedback and carried out further work to help refine our proposals. As a result, we have made a number of updates. Below is a summary of the key themes raised and the changes we have made.

Scale of Development

You said:
Questions regarding the scale of the development and its relationship with the wider New Forest, the National Park and Southampton Water.

We did:
The proposed commercial floor space has been reduced from approximately 190,000 sqm to 143,000 sqm.

Type of Business / Uses

You said:
There is a lack of clarity about the types of businesses that could be located at Fawley Waterside, including what is meant by digital industries.

We did:
While the outline planning application establishes a range of potential uses to maximise the opportunities for job creation and long-term investment for the local area, the exact mix will be determined at Reserved Matters. Data centres are one of the potential uses being considered.

Impact on Environment

You said:
What is the impact of the development on noise, lighting and the environment.

We did:
Further assessment has been undertaken and indicates that impacts on noise and air quality would not be significant. Lighting has been carefully designed and assessed to maintain the “dark sky” around the site, to minimise effects on the surrounding area.

Traffic & Road Safety

You said:
The increase in traffic generated by the development would have a negative impact on the local road network. Comments also addressed the safety of the existing roads and pathways.

We did:
Assessment has concluded that the surrounding road network can accommodate traffic from the proposed development. New walking and cycling measures to and from the site, together with a crossing on the B3053 near School Road/Church Lane, are also proposed.

Construction Impacts

You said:
Concerns raised regarding the construction works and impact on the residents, roads, noise and traffic. Major developments create dust and disturbance.

We did:
An outline Construction Traffic Management Plan will be submitted with the planning application. This will be developed and refined as the detailed reserved matters are brought forward. The phasing of the construction will mean different impacts at different times. Use of the dock for deliveries to the site will also be considered.

Ecology

You said:
What are the effects of the proposals on biodiversity, wildlife habitats and the surrounding marine environment.

We did:
All ecological surveys have been completed and a full analysis of the site, and the impact of development is underway for completion as part of the outline planning application. Biodiversity Net Gain is also being considered and measures will be undertaken to enhance the biodiversity of the site.

Visuals

You said:
What will the development look like, and what is its impact on the wider landscape?

We did:
Working with the Local Planning Authority, key public viewpoints were identified and used to test the proposed height parameters. The resulting parameter views have helped inform the maximum building heights and provide an indication of the likely scale of development.

Footpaths

You said:
Can a footpath be provided between Fawley and Calshot, and can access be improved from the King Charles III Coast Path to the proposed café on site?

We did:
The proposals include a permissive footpath linking Fawley and Calshot through the site and connecting to Tom Tiddler’s. A public route to the new cafe is provided from the King Charles III coastal footpath

Landscape & Visual Assessment

We recognise the importance of carefully considering how the development sits within its surrounding landscape, including views experienced by local residents, and users of the nearby Public Rights of Way, permissive paths, public highways and the waterway.

A comprehensive Landscape and Visual Impact Assessment has been undertaken to inform the design approach, ensuring that the proposals respond sensitively to surrounding settings.

Accurate images have been prepared to demonstrate how the maximum development envelope would appear from viewpoints agreed with the Local Planning Authority.

To understand the images, please note the following:

  • The dotted red line shows a development envelope illustrating maximum footprint and height.
  • It is not showing buildings; the dotted red line illustrates the area within which buildings could be located.
  • All buildings, including final footprints, architectural design and façade material will be subject to future planning applications.

Flood Risk

Flood risk has been a consideration throughout the refinement of the proposals.

The site being located alongside Southampton Water is at risk of coastal flooding both now and in the future. Climate change and rising sea levels are expected to increase this risk over time, so the development is designed to remain safe and resilient throughout its lifetime.

Since the first round of consultation we have developed in more detail two flood risk options and consulted with the Environment Agency. Both options will be presented in the planning application.

The options are as follows:

  • Perimeter Flood Defence: New flood defence features, such as earth bunds and flood walls, constructed around the edge of the site to help protect the development from coastal flooding and future sea level rise.
  • Land Raising: Development/plot areas raised to levels designed to remain above future flood levels, helping to ensure buildings, infrastructure and access routes are resilient to coastal flooding.

Neither of these measures will impact the overall height of development.
Whichever approach is taken, the development will incorporate measures to manage residual flood risk from extreme events, including flood warning and emergency planning procedures. This will help to ensure the site remains safe, both in present day and in the future, without increasing flood risk elsewhere.

Option 1

Option 2

Traffic and Transport

Operational Traffic Figures

Traffic movements associated with the proposed development have been assessed.
The table below shows predicted traffic movements from the development, compared with existing site traffic and full occupation of the site.

Trip Generation Comparison
[Two-Way, Total Vehicles]
Trip Generation Comparison
[Two-Way, OGV*]
AMPMDailyAMPMDaily
Existing Site Usage1941567056
Existing Site with Full Occupation365301140115
Proposed Development – Plot 18 as B24123183761246193
Withdrawn Application12691615146701619176

*Other Goods Vehicles (OGV) refers to commercial and freight-carrying vehicles that exceed 3.5 tonnes.

The Road Network

Our traffic assessments indicate:

  • While some delays will increase and certain junctions will operate close to capacity, the road network is expected to continue operating within accepted standards.
  • Major highway improvements are therefore not proposed. Instead, targeted measures will improve traffic flow, including updated signage and the potential for future lane designation changes at Dibden Purlieu (The Heath) Roundabout.
  • The B3053/Church Lane junction is predicted to remain within capacity, although delays for right-turning traffic from Church Lane during the PM peak may increase.
  • To address concerns about Church Lane being used as a shortcut, we are proposing changes to the junction with Marsh Lane that will encourage lower vehicle speeds and reduce the attractiveness of Church Lane as an alternative route.

Walking and Cycling Improvements

The proposal will improve walking and cycling links between Fawley and Holbury, which have been developed following feedback from the previous consultation. Two crossing options are being considered between School Road and Church Lane:

Option 1: Adjacent to Fawley Primary School, providing good access to local bus stops and the route between Fawley and Holbury.

Option 2: Closer to Church Lane, better serving people walking and cycling along Church Lane and creating an opportunity to remove the left-turn slip lane to help reduce traffic speeds.

Feedback is being sought on the preferred crossing option.

Fawley Road / Church Lane / Blackfield Road Improvements

Speed Limit

Following comments from local residents, potential reductions to speed limits are also being explored to improve conditions for walking, cycling and the local community.

The proposed speed limit changes are shown in the plans, and feedback is welcomed.

Existing Speed Limit
Proposed Speed Limit

Bus Connections

We currently do not anticipate that demand will be high enough to support bus services being extended to the site on a long term basis but we are speaking to Bluestar about this as an option. Should this not be possible, the alternative would be the provision of an on-demand minibus service between the Fawley Waterside and Fawley Square to provide a connection to existing bus services. This would also enable staff to take advantage of facilities within Fawley on their lunch breaks and after work.

Planning

Planning and Consents

Autumn 2026 – Spring 2027

Enabling Works

Off-site Infrastructure

Summer 2027 – Summer 2029

Sea Defence Works

Summer 2027 – Summer 2031

On-site Infrastructure

Summer 2027 – Summer 2037

Construction

Phase 1

Winter 2028 – Autumn 2035

Phase 2

Spring 2030 – Autumn 2037

Phase 3

Spring 2033 – Summer 2040

Phase 4

Summer 2035 – Autumn 2042

Key Benefits

Jobs and skills

At least 1,200 operational jobs created once the site is complete. Based on current behaviour patterns around 75% of these jobs would be for people living in the New Forest area. From apprenticeships upwards, this will help retain local talent and attract new skills to the area.

Improved access to the wider area

Provision of a new pedestrian link from the coastal path to the new cafe and a new pedestrian link alongside the site boundary connecting to the existing public rights of way.

Retention of former canteen

Fawley Waterside will provide a cafe in the former power station canteen building. By transforming the former power station canteen into a café, Fawley Waterside will celebrate the site’s heritage while creating a vibrant public space at the heart of the new development.

Landscape coastal edge

The landscape led approach will deliver new planting, green space and landscape zones across the site. Initial assessments indicate the development will provide a biodiversity net gain on the site.

Next Steps

Following this consultation, we will review the feedback to finalise the proposals before submitting an outline planning application to New Forest District Council later this year.

Early Autumn 2026

Second round of public consultation

Late Autumn 2026

Anticipated submission of the planning application

Spring 2027

Expected New Forest District Council Planning Committee decision

Consultation documents

  • September Exhibition materials
  • June Exhibition materials
September Exhibition materials
Exhibition boards pdf 9 MB Download Eye
Paper feedback form pdf 521 KB Download Eye
Exhibition invitation newsletter pdf 1 MB Download Eye
June Exhibition materials
June Exhibition boards pdf 11 MB Download Eye
June Paper feedback form pdf 191 KB Download Eye
June Exhibition invitation newsletter pdf 918 KB Download Eye